Meta-plan: how we get to a precise plan

This is deliberately a plan for making the plan. The scaffold (this repo) fixes the frame; the phases below turn the frame into specs precise enough to implement test-first. Each phase has an exit gate — we do not start implementation epics until Phase 4's gate passes.

Phase 0 — Frame (done with this scaffold)

  • Vision written (vision.md), seed ADRs drafted (0001 accepted, 0002–0006 proposed), C4 sketches, decision log started.
  • Gate: operator has read vision + ADRs and vetoed nothing fundamental.

Phase 1 — Requirements harvest

Collect the raw material the specs will be distilled from:

  1. Sample repos — operator provides 2–3 further representative self-service repo shapes (topic-style YAML, catalog JSON, tfvars); we re-create generic equivalents under examples/repos/ — never verbatim copies of any private content (D-002/D-008). In parallel, curate open-source corpora (kubernetes/org, JulieOps topologies, octoDNS zones, Backstage catalogs — candidates in examples/repos/README.md, OQ-16) as public test targets and demos.
  2. Rule archetype inventory — enumerate every rule class the archetypes in vision.md must generalize; for each: inputs needed (change paths, facts, permissions), decision semantics, failure mode. This becomes the acceptance bar for the policy frontends.
  3. Forge behaviour dossier — for GitLab and GitHub: exact API mechanics for resolvable threads, approvals, self-approval limits, bot identity, merge preconditions. Feeds ADR-0005.
  4. Prior-art review — OPA/conftest, Kyverno (syntax inspiration), Mergify, Bors/merge queues, Renovate's automerge, Prow/Tide, danger.js: what each got right/wrong for this use case; recorded per tool in docs/planning/prior-art.md.

  5. Gate: archetype inventory reviewed; every archetype has at least one concrete example change + expected decision written down.

Phase 2 — Decide the proposed ADRs

Run each Proposed ADR (0002–0006) through a weighted trade-off matrix + targeted spikes:

  • Spike A (policy): implement the bounded-change and ownership archetypes in raw Rego against a hand-written PolicyInput; then sketch the YAML equivalent; decide "YAML lowers to Rego" vs. "two evaluators" (OQ-3).
  • Spike B (e2e): boot GitLab CE as a testcontainer and in kind; measure boot time, RAM, flakiness; decide the CI default (OQ-6).
  • Spike C (plugins): wire a toy Keycloak-group provider twice — as exec provider and as go-plugin — and decide whether tier 3 ships in v1 (OQ-4).

  • Gate: ADR 0002–0006 moved to Accepted (or superseded), each with matrix + spike evidence.

Phase 3 — Contracts first

Freeze the five public contracts as versioned schemas with fixtures before any engine code: PolicyInput, Decision/Findings, Provider request/response, Forge-port conformance suite (as executable spec skeletons), and the adopter test fixture format (ADR-0014, D-010).

  • Gate: contracts reviewed; golden fixtures exist; openspec/specs/ epics written with REQ IDs, each REQ carrying Test: and Verify: per openspec/config.yaml.
  • Gate artifact (ADR-0017 §8, D-016): the strict end-to-end contract fixture — pinned target/merge result, renamed entry with stable identity, two required obligations, an expired typed fact, a missing required approval, expected DecisionRecord + PresentationModel + publication preconditions — validated against the same JSON Schemas as every example. No engine code before this fixture exists.

Phase 4 — Walking skeleton (first implementation slice)

Thinnest end-to-end slice, TDD throughout: CLI runs in a GitLab CI job on a kind-hosted GitLab sample repo → parses a one-field YAML change → evaluates one declarative rule → posts one resolvable thread or approves + merges → emits the JSON report. Everything real, everything minimal.

  • Gate: the L3 e2e for the skeleton is green and replayable; determinism gate active.
  • Adoption gate (D-012): Phase 4 is not "done" until one real repository (a personal/ demo self-service repo counts, a synthetic fixture does not) has run assent on live MRs. Deferred tiers (rego, gRPC, WASM, GitHub, serve, remote packs) unlock only with a named consumer — seams stay designed, contracts stay unfrozen until then.

Phase 5 — Epic execution

Spec-first, vertical slices per epic. The E-numbering below is the one that actually executed — each row names its spec under openspec/specs/ — and it matches the README feature-maturity table. (The Phase-2 proposed cut had E2 as a Rego frontend and E8 as the GitHub adapter; both moved to the deferred tier, so the numbering shifted.)

Epic Slice Spec Status
E1 Canonical change model: JSON + YAML (+ HCL/tfvars) p5-e1-canonical-change-model shipped
E2 Decision engine + CEL predicate backend p5-e2-decision-engine shipped
E3 Policy surface: assent lint hard errors + rule catalogue p5-e3-policy-surface shipped
E4 GitLab forge adapter: Snapshot / Resolve / Reconcile p5-e4-gitlab-forge shipped
E5 Provider host + builtins (HTTP/exec, gitlab-groups, ownership) p5-e5-provider-host shipped
E6 Adopter test harness (assent test) + assent compare seed p5-e6-adopter-test shipped
E7 E2E & conformance infra p5-e7-e2e-conformance shipped
E8 Renderer & presentation (ADR-0016 tier 0) p5-e8-renderer shipped
E9 Distribution & release (oss-playbook) p5-e9-distribution shipped (v0.1.0)

Follow-on epics cut during Phase 5, outside the E1–E9 sequence: EFE (p5-e-fileevents, whole-file match.fileEvents), PCS (p5-pcs-policy-comparison, full comparison-suite runner), AUD (p5-aud-audit-remediation, post-release audit remediation).

Deferred tiers keep their own numbers and unlock only with a named consumer (D-012): E10 GitHub adapter, E11 Rego backend, E12 serve (HTTP API), E13 remote packs — see the feature-maturity table in README.md.

Ordering constraint: E7 starts early (alongside E1) because every later epic's exit gate depends on it.

Standing rules

  • TDD mandatory; one logical change per commit; gitmoji-conventional commits.
  • No employer/internal references in any artifact (D-002). Sanitization check in CI later.
  • Open questions live in open-questions.md with OQ IDs; an OQ blocks the phase gate it is tagged with.